Ayr Wellness

Lakewood, New Jersey

Ayr Wellness required over 5MW of power to run its recently-commissioned 80,000 sf Lakewood, NJ, cannabis growing facility. Utility power was not available within a reasonable timeframe, which prompted Ayr to find alternative solutions to the utility supply.

DME, in collaboration with Kinsley Energy and Aggrekko, engineered a temporary power solution consisting of (6) 1,300KW natural gas engines for a total installed capacity of 6.5MW. DME engineered the power distribution at the site, cable tray layouts, natural gas supply, and grounding.

Project Type

Temporary Generator

Project Size

80,000 sf

Project Cost

Confidential

Project Completion

2022

Share